Re: Compute future cost with fresh data
by
ClosingAp Open Source Integrators Europe, LDA, Daniel Reis
Hello David,
We worked on a "cost roll up" feature to recompute product costs all the way up multilevel BOMs.
It tries to answer "if a component changes price, what components and products are impacted and how much".
We also factored in labour and operations costs, to show the impact of things like increases in worker hourly rates.
This is build to at the end update product standard costs, but you skip that part and just use the simulation/impact reports.
See OCA/stock-logistics-warehouse, PRs 1226, 1227 and 1289.
Thanks
Daniel
We worked on a "cost roll up" feature to recompute product costs all the way up multilevel BOMs.
It tries to answer "if a component changes price, what components and products are impacted and how much".
We also factored in labour and operations costs, to show the impact of things like increases in worker hourly rates.
This is build to at the end update product standard costs, but you skip that part and just use the simulation/impact reports.
See OCA/stock-logistics-warehouse, PRs 1226, 1227 and 1289.
Thanks
Daniel
On 06/05/22 13:31, David Beal wrote:
Hi all,My customer needs data about future costs for its final bom level products to adjust future sales prices (inflation time)
Odoo store cost concerning stock (my customer use average cost) in the warehouse but not the future cost.
Despite of this, you have with supplierinfo data about this future cost (or purchase amount at least).
Do you know a module allowing to compute cost depending of supplierinfo prices or any other approach ?
Thanks
Regards
_______________________________________________
Mailing-List: https://odoo-community.org/groups/contributors-15
Post to: mailto:contributors@odoo-community.org
Unsubscribe: https://odoo-community.org/groups?unsubscribe
--
DANIEL
REIS
MANAGING DIRECTOR
MANAGING DIRECTOR
M:
+351 919 991 307
E:
dreis@OpenSourceIntegrators.com
A:
Avenida da República 3000, Estoril Office B, #34
Reference
-
Compute future cost with fresh data
byAkretion France., David BEAL-
Re: Compute future cost with fresh data
byClosingAp Open Source Integrators Europe, LDA, Daniel Reis